NASA completes first series of Ares engine tests

12 May 2008

NASA engineers have completed the first series of tests in the early development of the J-2X engine that will power the upper stages of the Ares I and Ares V rockets, components of NASA's Constellation Programme. Ares I will launch the Orion spacecraft that will take astronauts to the International Space Station and then to the moon by 2020. The Ares V will carry cargo and components into orbit for trips to the moon and later to Mars.

NASA conducted nine tests of heritage J-2 engine components from December to May as part of a series designed to verify heritage J-2 performance data and explore performance boundaries. Engineers at NASA's Stennis Space centre in Mississippi conducted the tests on a heritage J-2 "powerpack," which, in a fully assembled engine, pumps liquid hydrogen and liquid oxygen into the engine's main combustion chamber to produce thrust. The test hardware consisted of J-2 components used from the Apollo programme in the1960s through the X-33 programme of the 1990s.

"This series of tests is an important step in development of the J-2X engine," said Mike Kynard, manager of the upper stage engine for the Ares Projects at NASA's Marshall Space Flight centre in Huntsville, Ala. "We started with a number of objectives and questions we needed answers to as we work to complete designs of the J-2X engine. The data we have gained will be invaluable as we continue the design process."

Data obtained from the tests will be used to refine the design of the J-2X pumps and other engine components to provide the additional performance required of this new engine. The J-2X engine is being designed to produce 294,000 pounds of thrust; the original J-2 produced 230,000 pounds of thrust.

The main objectives of the series were to resolve differences in heritage turbopump performance data and recent component-level tests, and investigate vibration and pressure drops through the turbopump inlet ducts. Tests in the series ran for durations up to 400 seconds and at power levels up to 274,000 pounds of thrust.

After the data from the test series has been reviewed and objectives met, Stennis will begin readying the test stand for the next series of tests, said Gary Benton, the J-2X project manager at Stennis.

Marshall manages the J-2X upper stage engine for the Constellation Program, based at NASA's Johnson Space Centre in Houston. Under a contract awarded in July 2007, Pratt and Whitney Rocketdyne (PWR) will design, develop, test and evaluate the engine.

"These powerpack tests provided us with very good data to help as we move forward in the designing and developing of the J-2X," said John Vilja, PWR's programme manager for the J-2X. "It's truly exciting to witness and be part of the future as it's unfolding and these successful tests are a tangible piece of that future."

REF XQQAS XQQSE XQQTY


DSD Home Page
DSD's News Index DSD welcomes Feature Articles for publication

editor@defence-data.com

Delivered to your desk and it's Free!

DSD is published by Defence Data Ltd

Copyright(c) 1996 - 2007 Defence Data Ltd. All rights reserved. Reproduction in whole or in part in any form or medium is prohibited except as provided in the Conditions of Use. The Defence Data logo is the trademark of Defence Data Ltd. Defence Systems Daily, and DSD, are the trademarks of Defence Data Ltd. By using this Web Site, you agree to all of the Conditions of Use